FIRST ANNUAL MONITORING MEETING OF THE PROJECT

01/02/2017

First annual monitoring meeting of the project (Barcelona and Planeses, February 1, 2017). The first annual follow-up meeting between Pepa Diamantopoulos, as a member of the monitoring team of the NEEMO-IDOM project (the company hired by the European Commission to monitor and monitor the project’s implementation) and the partners of the POLYFARMING project was carried out in Barcelona and the Planeses farm. The meeting took place initially at the CREAF facilities and, once this part of the session was over, it was moved to the Planeses farm, where the project’s demonstration activities are carried out. The meeting served to monitor the progress that had taken place in each of the actions of the project (with only 7 months of duration so far), review the planning status of future actions, assess the expenditures made so far, and discuss some doubts that the project partners had.